To notify Yass Valley Council of damage to roads, fallen trees, burst water mains etc please call - 6226 1477 or complete an online Customer Service Request.
The recent climatic conditions continue to prove challenging for ongoing road maintenance activities with recent heavy rainfall causing localised washouts on some roads. Targeted unsealed road maintenance is being undertaken to improve road drainage (and identify possible new locations where drainage may be required), reshape and widen roads, remove roadside vegetation and re-use the accumulation of gravel along the side of the road as part of the unsealed grading program. Unsuitable material is also being removed from the road edge to assist in allowing water to drain from the road surface and is not used on the road. Additionally, more signs and guideposts will appear on the road sides as we implement this program to improve road safety and better road definition. The extent of this work varies on each road and may delay the expected commencement dates of some roads listed but not the order of roads being graded.
While this work will take some time to complete it will allow our roads to better cope with normal upcoming rain events while at the same enable an assessment of road conditions to be conducted as we move through the Council area to ensure that depleting suitable natural gravel supplies are used responsibly.
Works completed or in the progress for the period 9 June - 12 JuneWhere works have been delayed, the previously advised dates have been revised to reflect changes to the program, brought about by unexpected delays in current projects caused by weather, additional works required, machinery breakdowns and the like. Please refer to the Proposed Works listing below for updated information.
Unsealed Road Program StatusMarked Tree Road
CompletedMajura Lane, Sutton
UnderwayWargeila Road
UnderwayYass River Road - Booths Crossing
UnderwayDairy Creek Road
Completed Sawyers Gully Road Underway Browns Lane Starts 22 June Noyes Lane Starts 24 June Sealed Road Program Site Works Status Various Asset inspections Underway Back Creek Road - Segment 6 Gravel re-sheeting Underway Stormwater Drainage Maintenance Drainage maintenance Yass River Road (Booths Crossing) Completed Drainage maintenance Back Creek Road - Segment 1 (from Sutton Road) Underway State Roads Control Ground Vegetation Completed Pothole and guideposts maintenance Underway Heavy Patching Sutton Road - between Murrumbateman Road and Gundaroo Completed Back Creek Road intersection with Sutton Road Completed Wargeila Road - Segment 7 Underway Black Range Road - Segment 11 & 12 Underway Regional Roads Maintenance Pothole patching, guide posts Underway Various roads - asset inspections Underway Other projects Work Roadside Noxious Weeds ControlCompleted Shaw Street area (African Love Grass) Council ponds off Coolalie Rd (Serrated Tussock) Mountain Creek Rd Wee Jasper Rd to the ramp Yass River to Gundaroo end Yass Valley way from Yass to Barton Yass Valley Way from Faulder Ave to roundabouts Selected areas of Dog trap Road
Starting 9 July Lachlan Valley Way Burrinjuck Road Clarks Lane
Capital Works - Pavement Rehabilitation Wee Jasper (Road Segment 69 between Gums Lane and Good Hope Road) - Underway15 June 2020