Council and/or contractors will be undertaking roundabout works at the intersection of Gill and Church Streets commencing Thursday, 7 January 2019, for a period of approximately five (5) weeks.
These works will be undertaken in the following stages:
Building of Roundabout – approximately two (2) weeks; Surfacing Works – approximately one (1) week; Island Construction – approximately two (2) weeksDue to the size of the Gill/Church Street intersection, all aspects of the construction will at times involve traffic control with lane closures and detours.
Council has endeavoured to schedule works to limit the impact on the general public, including halting works during the Goldfield Ashes weekend, however Council acknowledges that the works may cause inconvenience and appreciates the public's cooperation.
Should you require any further information, please contact Mark Gladman, Urban Coordinator on 4761 5300.
Aaron Johansson Chief Executive Officer
OGG 6 December 2018