Roundabout works starting in Chinatown
Shire of Broome 1 Mar 2019
Roundabout works starting in Chinatown

Released 1 March 2019

Work to upgrade the roundabout at the intersection of Carnarvon St and Short St in Chinatown will get underway this Monday 4 March and is scheduled to be completed by Sunday 10 March.

Work on the project was delayed by a week following tides of more than 10m that soaked the subsurface of the site.

The project will require the roundabout and a section of Short St up to the exit from the Paspaley Plaza rear carpark to be closed to vehicles, with detours and traffic management in place.

The majority of construction will be carried out at night to minimise disruption to trade in Chinatown from heavy vehicles entering and exiting the site.   

Record rainfall during the 2017/18 wet season caused permanent damage to the subsurface beneath the roundabout that will require excavation and soil stabilisation to be carried out before resealing and asphalting.

Similar work has been carried out in recent weeks on Frederick St, Lullfitz Dve and Cape Leveque Rd.

Temporary repairs were undertaken in early and late 2018 to allow traffic to continue using the roundabout until the permanent upgrades could be carried out.

The work is being funded through the WA Natural Disaster Relief and Recovery Arrangements that were activated following the extreme weather of the 2017/18 wet season. 

Construction will be carried out by Broome firm McCorry Brown Earthmoving and the project has been timed to dovetail with work on Carnarvon St as part of the Chinatown Revitalisation Project.