Council will be starting works to expand the Skennars Head Sports Fields in May 2019.
The $2.2 million project was identified as a key priority in the Ballina Shire Open Space Strategy to help cater for our community's growing population and participation demands.
The improvement works will include:
new senior playing field area new junior playing field area sport field lighting and irrigation improved drainage additional parking with new site entryThis project is possible due to $1,285,000 in Council funding and $990,000 in funding from the State Government Stronger Country Communities Fund.
Site access: Council will endeavour to keep disruptions to a minimum for field users during these works. Council is liasing directly with sporting clubs during these works.
Anticipated timeline: May 2019 - late 2019.
Contractor: Synergy Resource Management
Investment: $2,275,000
More information: For more information contact Council's Open Spaces Development Officer on 1300 864 444.
Plans