Installation of panels on the east side of Joondalup Drive.

PLEASE NOTE THIS INFORMATION IS PROVIDED BY MAINROADS WA

The installation of panels on the east side of Joondalup Drive will be undertaken from Tuesday night, 10 September through to Saturday morning, 14 September 2019.  

The panels will be installed using the same method as the panels on the west side. A crane will install them one-by-one, placing them on concrete pads. They will be propped up until the ramps are backfilled and held in place by permanent strapping.

The roads will remain open, however there will be lane closures. These night works will start after PM peak and be finished before AM peak.

Residents may hear and feel these works.  Where possible, noiser activities will be undertaken before 10pm.