Byron bypass construction break over Christmas and New Year period
Byron Shire Council 13 Dec 2019
Byron bypass construction break over Christmas and New Year period

Published on 13 December 2019

Construction on the Byron bypass project will pause for a two week break over the Christmas and New Year period from Saturday 21 December to Sunday 5 January.

“Stage 1 will be approximately 70 percent complete by Christmas,” Director of Infrastructure Services Phil Holloway said.

“While it was due for completion before Christmas this year,  the presence of protesters on site in July, and discovery of Mitchell’s Rainforest snails in previously unknown habitat adjacent to the Stage 1 footprint at Burns Street, required works to be reprogrammed. For these reasons there is now a delay to this stage of the project,” he said.

“Council is awaiting the outcome of the EPBC referral from the Department of Environment and Energy before completing the final work in Stage 1 and commencing the proposed work for Stage 2,” he said.

“Along with the new road construction, some of the additional construction highlights include the installation of a new two-cell box culvert at the northern end of the project, a new 300 metre shared path, underground electricity, new street lighting which is now operational, relocation of Telstra and other utilities and improved storm water drainage.”

There will be no traffic controllers on the bypass site over Christmas. The community are urged to pay careful attention to the signage in place during this time.

The road between Shirley Street and Glen Villa Resort will be sealed, and signage guiding motorists through the traffic diversion will remain in place.

Temporary footpaths will be available for pedestrian access throughout the works area.

A green coloured dust suppression agent will be used on exposed road edges as a temporary measure during the break.

“The green agent is coloured with vegetable dye and is a common agent used in construction projects. This substance will break down following final landscaping work and has no detrimental environmental effects.” Mr Holloway said.

“Not all work on site has been finalised so please be aware some sections of sealing are temporary, particularly at the Burns Street intersection where no pavement reconstruction works have commenced to date. In these locations it is possible that potholes could form over the break,” he said.

Butler Street Reserve will remain closed during the holiday period.

For any emergency issues over the Christmas break, Hazell Bros Community Liasion Officer will be available on 0409 973 673. For all media enquiries please contact Annie Lewis on 6626 7320.