Planned pavement maintenance works for Bega and surrounds
Bega Valley Shire 18 Jun 2020
Planned pavement maintenance works for Bega and surrounds

Photograph: Crack sealing in action

18 June 2020

Planned pavement maintenance works are scheduled to commence Friday 19 June on select streets within Bega, North Bega, Tarraganda, Coopers Gully, Buckajo and the Brogo area.

Crack sealing will be carried out on the following streets:

Baker Street, Bega Glen Mia Drive, Bega Ridge Street, North Bega Lagoon Street, North Bega Healey Street, North Bega Parrabel Street intersection, North Bega Nullica Road, Tarraganda Mt Pleasant Road, Coopers Gully McLeods Road, Brogo Daisy Hill Road, Buckajo

 The work is expected to take two days including the weekend period.  Council is undertaking the works to maintain pavement longevity.

Motorists can expect lane closures and short delays as a result of traffic control measures used to facilitate the works.  Additional travel time should be allowed during the period of works.

For more information, please contact Council’s Civil Assets Superintendent, Gary Louie on (02) 6499 2222

END

Rate This Page Share This Page