Published on 25 July 2020
After an unsuccessful attempt yesterday (24 July 2020) to get Belongil Creek to open naturally to the ocean by scraping the sandbank back to water level, Council today engaged earth-moving equipment to manually open the creek mouth..
Water levels in the creek reached 1.25m this morning, causing flooding and inundation in parts of the Belongil catchment. With more rain predicted over the weekend water levels were expected to get higher, prompting Council to open the sandbank that was blocking the creek mouth.
Council has a licence from the NSW Government to instigate ways to encourage the creek mouth to open when water heights reach 1.1 metres.
Belongil Creek is an ICOLL, an intermittently closed or open lake or lagoon, which opens to the ocean. When the sandbank closes the entrance to the creek, water levels build up and heighten the risk of flooding in the Belongil catchment.
“The management of ICOLLS like Belongil Creek are complex because any opening to the ocean can cause a fish kill because the sudden rush, or drawdown of water, can quickly strip the water of oxygen,” Phi Holloway, Director Infrastructure Services, said.
“We have done everything we can to try to minimise this and we were hoping the scraping of the sandbank yesterday may have seen the creek open naturally but this didn’t happen.
“With the water levels in the creek so high we need to manage the risk of flooding with the Byron Bay CBD particularly vulnerable,” Mr Holloway said.
Council notified National Parks and Wildlife Service, the Arakwal Corporation, NSW Fisheries, the Cape Byron Marine Park and Crown Lands yesterday that it was starting work on opening Belongil Creek to open to the ocean.
Council staff are now closely monitoring the situation at Belongil Creek.
For more information about ICOLLS visit www.byron.nsw.gov.au/Services/Environment/Coast-and-waterways/Estuaries-and-ICOLLs/Managing-ICOLLs.
For media enquiries contact Annie Lewis, Media and Communications Coordinator, on 6626 7320.