3 March 2021
Stage A of the Penguin Foreshore Remediation and Upgrade Project construction is progressing and all facets of the site are actively busy. The main pathway continues to be built from Penguin Creek including the upgrading of the new beach accesses. Installation of the main verti-block wall has commenced adjacent to the foreshore playground, including a new ramp access. The main rock revetment wall is nearly completed and the kerb and channel have just started along Surf Club Road. Please see aerial pictures below, taken on 27 February.
The Stage B design is available to download below.
Stage B - Penguin Foreshore Remediation and Upgrade Project- DesignClick on the green button for more information on the Penguin Foreshore Remediation and Upgrade project: