COUNCIL COLUMN - 25 OCTOBER 2021
Lachlan Council News 25 Oct 2021

NEXT ORDINARY MEETING OF COUNCIL

Wednesday 27 October 2021 - Tottenham Memorial Hall commencing at 2:00 pm. An invitation is extended to the community to attend the meeting. (Meeting subject to current health orders)

AUSTRALIA DAY 2022

Have you submitted your nomination for the Lachlan Shire Local Citizens of the Year Awards? For more information please contact Council’s Executive Assistant Paula Ewing on 02 6895 1900. Nominations close Friday 19 November 2021 and forms can be downloaded from the Council website https://www.lachlan.nsw.gov.au/council/council-forms.aspx

2021 LOCAL GOVERNMENT ELECTION

Lachlan Shire Council elections will be held on Saturday 4 December 2021. Council’s customer service teams at Lake Cargelligo and Condobolin can accept paper nomination forms with full payment up until 12 noon, Wednesday 3 November 2021. Late nominations cannot be accepted under any circumstances. Candidates can find information on Council’s website https://www.lachlan.nsw.gov.au/council/council-elections.aspx or go to the NSW Electoral Commission website - www.elections.nsw.gov.au to nominate online.

EMPLOYMENT OPPORTUNITIES

▪ Community Care Worker - casual position based in Tottenham. Contact: Kristy Simpson - Closing date15 November 2021

▪ Customer Service / Service NSW Officer

Permanent part-time position in Condobolin. Contact: Eiline Smith -

Closing date 1 November 2021

CALL OUT TO MUSICIANS AND BANDS 

Expressions of interest are sought from musicians who would like to participate in the Lachlan Live and Local program, delivered in partnership with the Live Music Office and APRA AMCOS. Musicians participating in Live and Local are given the chance to showcase their talents and get paid, connect with other local industry professionals, build on their professional experience and contribute to the growth of the live music scene. Click the link to access the expression of interest form-https://www.lachlan.nsw.gov.au/busine.../live-and-local.aspx

BREASTSCREEN VAN IN TOTTENHAM

BreastScreen NSW mobile screening van will be in Tottenham between Saturday 30 October and Monday 1 November 2021 at the Tottenham Multi-Purpose Health Service. To make a booking, visit https://book.breastscreen.nsw.gov.au or call 13 20 50.

RECREATION

▪ Council swimming pools in Condobolin, Lake Cargelligo, and Tottenham are now open for the summer swimming season.

▪ Stage 3 – installation of Condobolin cricket and soccer field irrigation in progress.

▪ Tottenham tennis court lights – footings complete and pole relocation progressing.

▪ Landscaping at the Condobolin Jockey’s Memorial in progress in partnership with TAFE.

ROADS

▪ Grace and Foster Street intersection, Lake Cargelligo – asphalting of intersection commenced this week, with a completion date of Thursday 28 October (weather permitting).

▪ Resealing of Grace Street from the end of asphalt to Johnston Street will be completed by Friday 29 October.

▪ SR 120 Merribogie Road – reconstruct and widen 7km. The first 2km was sealed last week.

▪ SR 1029 Tullibigeal Road – construct and seal 13km from the end of seal to Lachlan Valley Way – sealing completed 21 October.

▪ Innes Street, Officers Parade – footpath construction continuing.

▪ Gum Bend Lake – sealing of tracks commenced this week.

▪ Maintenance grading on the unsealed road network is continuing in preparation for the forthcoming grain harvest.

▪ All shire roads are expected to reopen this week as the Lachlan River level falls at Condobolin week commencing 25 October.

▪ For specific road hazard or road condition concerns please contact Council on 02 6895 1900.

UTILITIES

Condobolin water supply shutdown - Following recent successful trials, Council will be undertaking critical remediation works at the Condobolin reservoirs on Wednesday 27 October 2021. This will result in a major supply interruption across the entire Condobolin water network between 11:00 pm and 5:00 am (6 hours). Residents in the surrounding areas to the reservoirs may experience some noise due to pumps running 24/7. Please ensure that pets are safe and secured.

Condobolin Borefields II Project - Pipeline works progressing with the contractor clearing the site. It is anticipated that the pipeline construction will start in the first week of November 2021.

INFRASTRUCTURE AND COMMUNITY BUILDING PROJECT UPDATES

Gum Bend Lake amenities - blockwork complete and roof construction underway.

Condobolin Animal Shelter - foundation prepared with slab to be poured this week.

Condobolin Youth Centre – kitchen installation nearing completion.