Three road and two culvert construction crews are working on the Clarence Way project between Bonalbo and Urbenville.
The culvert crews are working ahead of the road crews replacing culverts before the road construction begins.
This multi-million dollar project is expected to take until mid-2025 to complete.
Crews continue to undertake drainage works on the Bruxner Highway at Mallanganee Range in preparation for the pavement works, while work on Kyogle Road has been completed.
Resealing works on Short Street, Kyogle, is continuing.
Maintenance grading is occurring in the Paddys Flat and Dyraaba catchments.
Council’s Jetpatcher is patching potholes on Clarence Way, while another pothole crew is working on Fawcetts Plain Road.
Construction work continues on the new Back Creek Bridge on Kyogle Road, Askews Bridge on Askews Dip Road, Eight Day Creek Bridge on Needhams Road and Gambleys Bridge on Gambleys Road.
Station Road No 2 Bridge was completed this week and is now open to traffic. Work has paused on the new bridge planned for Rodgers Road.
Repairs to landslips on Gabal and Dugans roads are ongoing, while remediation of the three major landslips on Lions Road is expected to be completed by the end of this month.
Contractors have completed Stage 2 of repairs to the landslip under Geneva Bridge and are currently demobilising the site.
Council is slashing verges on Gradys Creek Road and Bruxner Highway and will then head to Findon Creek Road.