As works continue to progress on the redevelopment at the Moree Artesian Aquatic Centre, this week, work will commence to prepare the site for the 50-metre pool, with the clearing of the vegetation.
Following on from that, Council has engaged a major local company to commence the earthworks to further prepare and stabilise the site.
The next stage in the site stabilisation will be laying the pier foundation in an area of 50m x 25m, where 180 piers/piles will be drilled into the ground up to 13-metres deep.
These foundation works are critical to the stabilisation of where the 50-metre pool will ultimately sit.
What has been occurring. GymGym users have step into a new era of fitness with new equipment and 15mm rubber impact flooring tiles. (As seen in the image right)
Active PoolThe Active Pool has had the cement poured, each pour needing 6 weeks to cure. Alongside of the concrete pouring has been the commencement on the pool wall and scum gutter/wet area.
Wellness PoolThe form work has been installed for a concrete pour that will form the walls in the Wellness Pool. (As seen in the image below)
Wellness StudioExpression of interest in the wellness treatment spaces for wellness and allied health professionals, such as Massage Therapists, Beauty Therapists, Physiotherapists, Osteopaths, and Myotherapists to occupy the rooms at the Wellness Facility are welcomed. Expressions of Interest should be sent via email to This email address is being protected from spambots. You need JavaScript enabled to view it.
“It was fantastic to see so many utilising the pools and waterslide on Australia Day, with 144 people enjoying the free entry offered between 1pm to 3pm”, informed General Manager, Kelvin Tytherleigh.