In great news for motorists, the bridge over Back Creek on Kyogle Road was opened to traffic this week, as was the new bridge on Rodgers Road.
The new Needhams and Gambley Road bridges were completed earlier this month, while construction of new bridges on Hansen, Yabbra and Ryans Creek roads is continuing.
Work to remediate the Forest Road landslip was completed last week, and work on the Clarence Way landslip should be finished today.
The recent wet weather has delayed work on the Gabal Road landslip repairs, and that work is now not expected to be completed until 8 March.
Council has also repaired a landslip on the MacQueens Road. Council has so far repaired 54 of the 99 major landslips which occurred after the 2022 flood event.
Flood damage repairs on the Clarence Way south of the Bruxner Highway are now complete. Council has four crews working on the upgrade of the Clarence Way between Bonalbo and Urbenville.
Work on the rehabilitation of a 3.5km section of Ettrick Road, and the Transport for NSW project on the Bruxner Highway at Mallanganee Range is continuing.
Council is undertaking maintenance grading in the Cawongla catchment and the Duck Creek area. Pothole crews are working in the Afterlee area.