Shire of Boddington 2 Mar 2025

Published on Sunday, 2 March 2025 at 11:58:00 AM

The drainage system, water main, and fire hydrant have been successfully installed, marking a significant milestone in the project. The next steps will involve carrying out bulk earthworks, followed by sealing and kerbing.

The main components of the project are on track for completion by the end of March, with landscaping work planned for a later stage.

For more information on the Town Centre Revitalisation Project, visit the project page here. 