Friday, 12 October, 2018
The flood recovery program, as a result of the December 2017 flood event, is nearing completion, with contractors scheduled to finish works in December 2018.
“We are so pleased to advise the program is nearing completion and have heard wonderful feedback from our community about the quality of the repairs so far.”
Council has allocated $250,000 for additional upgrades, with works started on Killeens Hill Road and forecast to commence on the following roads in the coming weeks:
Hills Road
Mackrells Road
Balmattum Road
Galls Gap Road
Council will provide further advice to the community in regards to necessary road closures associated with these works.
If you have any questions in relation to the flood recovery program or the additional upgrades, please contact Council Offices on 1800 065 993 or email